NASA MIR PROGRAM
Mir 24 / NASA 5  Status

Date:	Wednesday, August 27, 1997
Mission Day:	Mir 24 / NASA 5  MD  22/104

Mir 24 CDR 	Anatoly Solovyov
Mir 24 FE		Pavel Vinogradov
NASA 5 FE		Mike Foale


Mir STATION SYSTEM/SUBSYSTEM ACTIVITIES

NOTE:  AT APPROXIMATELY 2013 DMT A DOWNLINK OF THE SPEKTR INTERNAL VIDEO WAS INITIATED.
THIS WAS NOT THE VIDEO SCHEDULED TO BE DOWNLINKED.  WHILE THE CREW INDICATED THAT THE 
VIDEO QUALITY ONBOARD WAS HIGH, THE DOWNLINK RECEIVED WAS EXCEPTIONALLY POOR.  

40-50A have been routed from Spektr to Kvant-2, and 90 A have been routed to Krystall.  Ventilation and thermal control are active in Krystall.  Crew work continues on Krystall and Kvant-2.  Priroda is not expected to be powered until after the September 3ish EVA.

On Monday, the crew was unable to start an oxygen generating canister because the 
striker mechanism (on the filter/striker assembly) was too worn out to ignite the 
primer.  Flight controllers contacted Mir-23 commander Tsibliev to locate the three 
spare assemblies on board, and the unit was changed out late Monday night.  Since then,
the crew has used three canisters per day.

There were also a number of problems restarting the Kvant-1 Elektron following the 
I/EVA.  On Monday at approximately 2040 DMT, it was restarted, although it was again 
shut down with purging Tuesday afternoon due to suspected thermal problems.  After 
several attempts, Elektron has been successfully reactivated (approx. DMT 1430 today) 
following the disconnection of temperature sensors on the electroyzer within the fluid 
unit.  The temperature of the fluid unit remained stable at 24°C throughout the day.  
TsUP indicated that if the temperature did not rise significantly, the crew should 
leave Elektron activated overnight and check the temperature again first thing in the 
morning.

The condensate reclamation system (SRV-K) is on but crew reported no water flow into 
the system earlier this week.  In between other activities, specialists at TsUP are 
working this problem.

Mir PAYLOAD ACTIVITIES
Greenhouse Daily Operations
Interactions
Private Medical Conference 

DATA MANAGEMENT
On-Board - Nominal
Network Status - Nominal
Ground Facilities Status  - Nominal

OPERATIONS
Procedures/Timelines  
The timeline for Thursday was received, translated, and forwarded to the POSA.

Experiment Operations

Greenhouse - Mike was told that Greenhouse operations do not carry over into NASA-6, 
and that all plant materials would be returned on STS-86. He was also given information
on plans for plant fixation, which is tentatively planned for one week after the EVA. 
Mike reported that half of the plants had siliques. The plants with siliques were 10cm 
in size, and those without siliques were 6cm in size. He reported that in the past 2 to 3 plants were placed in each bag for fixation.
Interactions was also completed today.

Experiment Hardware
MIPS laptop - One of the retrieved items was his personal laptop. This is the laptop 
that had a COSS hard drive installed along with a PCMCIA card. He mentioned that the 
laptop LCD screen was blank upon power up, and that it was at ambient temperature when 
he tried powering it up. As soon as the TsUP became aware of the safety board's concern 
over the battery, Mike was informed (today) to not attempt to power the laptop. He also
stated that he believes he now has all the hard drives that he brought with him.

Vacuum Cleaner - The vacuum cleaner has been tested by the crew and is fully 
operational.

Priroda Hardware Checkout- Draft radiograms with TsUP comments for the repowering of 
hardware were faxed to the POSA. It is recommended that when possible, hardware 
checkout be performed during the same session as restart of experiment operations. 
We will perform  PUP checkouts as soon as practical and only after it is certain that 
the Priroda is relatively free of condensation in the area behind the PUP units. It is 
unclear as to when power to the Priroda will be available for hardware checkout / operation
but it will not occur prior to the EVA. The current priority of hardware checkout is as
follows:
PUPs, MIPS laptop/controller/ODD, MGBX, SAMS, CGEL hardware, MiSDE, OPM.
Optical Properties Monitor - It is generally agreed that the OPM should be restarted as
soon as possible, however, since the PI's have requested the use of contingency 
procedures, TsUP is requiring that the procedures undergo Procedure Verification since 
they are not in the onboard FDF. This is currently scheduled to occur Friday September  
5th during the upcoming training sessions in Houston. A Procedures Change Request is 
required to be submitted as part of this process. We are still waiting for official 
SMART board recommendations/approval.

Thermo-electric Freezer - The TsUP has received the RR for the inspection of the TEF 
unit. It is currently under review.

Stowage/Transfer
Mike identified the following items as retrieved from Spektr during the IVA:
	F2 camera for Greenhouse and mounting bracket
	35mm lens for NASA camera
	1 MIPS laptop w/red (0326) power cable
	Personal COSS HD & PCMCIA cards
	Old Optical disk kit (nomex) w/ 10-15 unlabelled disks 
	   (presume unused?)
	Spare MIPS hard drive
	Vacuum cleaner WITHOUT spare parts or bags
	Notebook containing Mike's real-time inventory lists 
	Personal photos

Mike reported that the Greenhouse leaf bags were NOT retrieved.

SMP/Medical
Mike began pre-EVA Russian medical exams.  Today he is scheduled to complete MK-6 Body 
Mass Measurement, MK-7 Leg Circumference, and MK-8 Hand-operating a Bicycle Ergometer.  MK-1 ECG is timelined for tomorrow.

A Private Medical Conference (PMC) was conducted from 2003 to 2013 DMT via Altair.  
No mission impact.

Mike asked to delay the video conference with his family until after the EVA.

Environmental Parameters (Previous 24 hour period)
Parameter	Min.	Max.	Nominal Range 
Pressure (mmHg) Base Block	615	624	660 - 850
ppO2 (mmHg)*	143	148	140 - 200
ppCO2 (mmHg)	4.5	5.3	up to 8.0
ppH20 (mmHg)	10.7	13.2	8 - 14
Humidity (percentage)	50	59		30 - 75 
Temperature (°C) base block (BB)  	23.2	24.6	18 - 28


 
COMMUNICATIONS SUMMARY
A/G with Consultants Group
10:39-10:48	CPA status.
	Greenhouse overview, status of plants, and information for fixation.
	Spektr inventory.

EVA STATUS - The shift flight director informed MOST that the first suited run 
onboard for Mike has been scheduled for September 1.  The outcome of this run, 
including Mike's thoughts on it, will be factored in to the decision on the EVA date.

ISSUES - None  

PLANNING
MIR 24 / NASA 5 MD 22/104
Mir Payload Activities
Greenhouse Daily Operations

Other Activities
EVA Prep Activities
Mir Operations Support Team - (MOST)