Overview
This feature is useful when
planning on WBS elements and internal
orders for the life of a project. However,
it can cause inaccurate numbers if
planning on cost centers.
You can use the Summary Statement and
the Account Managers Report to reflect the
total planned amounts over all fiscal
years. The Account Managers Report allows
you to enter a range of fiscal periods and
years to see planned amounts across fiscal
years in one report run. When you run the
Summary Statement, you can enter only one
fiscal period and year at a time. If you
want to see planning for the next year,
you need to run the Summary Statement for
the next fiscal year.
top
Plan
for Multiple Fiscal Years
1. Create a plan for the first fiscal
year and save it.
2. The Initial Screen maintains the
parameters for the plan. Change the
From period, To period, and
Fiscal Year fields on the Initial
Screen to plan for the next fiscal
year.
3. Click the Overview button
and create the plan for the next fiscal year.
4. Save the plan. Repeat for subsequent
fiscal years.
top
An
Example
In the example below, $12,000 is
planned on a WBS element from period 3 of
fiscal year 2000 to period 11 of fiscal
year 2001. Fiscal year 2000 and fiscal
year 2001 each contain $6,000. You can use
sap-edu, the Practice environment,
to work on this example.
Plan the
First Fiscal Year
1. Set the plan parameters for the
first fiscal year.
2. On the Initial Screen:
- Enter the plan version of your
school or area in the Version
field.
- Enter 3 in the From period
field and 12 in the To period
field.
- Enter 2001 in the Fiscal Year field.
- Enter a WBS element number in the
WBS element field.
- Enter CEMIT-0 in the Cost
element or group field.
- Click the Free radio button.
3. Click the Overview button
to go to the Overview Screen.
4. Enter 6000 in the Planned
Costs field. For this example, plan
the entire amount on cost element 420226
Materials and Services and set the
distribution key to automatically
distribute evenly across fiscal periods
(Dist Key = 1).
5. Select the row by clicking in the
left box.
6. Click the Period button
to see the distribution across periods on the Period Screen.
7. Click the Save button
to save the plan.
Result: The Initial Screen
appears with the parameters still set.
Plan the
Next Fiscal Year
1. To continue the plan into the next fiscal year, on the
Initial Screen:
- Enter 1 in the From period
field.
- Enter 11 in the To period
field
- Enter 2002 in the Fiscal year field.
2. Click the Overview button
to go to the Overview Screen.
3. Enter 6000 in the Planned
Costs field. Again, for this example,
the entire amount is planned on cost
element 420226 Materials and Services and
it is automatically distributed evenly
across fiscal periods.
4. Select the row by clicking in the
left box.
5. Click the Period button
to see the distribution across periods.
6. Click the Save button
.
Result: The $12,000 is now
planned across the two fiscal years for
the life of the project.
Once your plan is saved, you can run
the Summary
Statement or the Account
Managers Report to check your plan
against revenues and expenses.