Tasks
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
beland
|
done
|
|
2 days
|
|
Task:
Write document describing evaluation critieria for Productivity Suite.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
amb
|
|
|
2 hours
|
|
Task:
Coordinate revision and sign off on Beland's Criteria document.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
alexp
|
|
|
|
|
Task:
Send basic Star Office issue history files to Richard Garcia.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
rlgarcia
|
done
|
|
|
|
Task:
Produce first draft of Master List of Star Office Issues.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
amb
|
|
|
|
|
Task:
Coordinate input and sign off on the Master List for submission to Sun.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
wdc
|
|
|
|
|
Task:
Get Master List into Sun.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
amb
|
|
|
|
|
Task:
Get items on Master List resolved by coordinating with Sun, and MIT
personnel.
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
alexp
|
|
|
|
|
Task:
Produce Star Office 5.2 Locker
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
wdc
|
|
|
3 hours
|
|
Task:
Get Star Office Non disclosure document between Sun and MIT
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
wdc
|
|
|
10 hours
|
|
Task:
Get Source Evaluation document signed between Sun and MIT
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
wdc
|
|
|
|
|
Task:
Get Star Office evaluation source from Sun
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
othomas
|
|
|
|
|
Task:
Evaluate proper scope for Star Office. Should it become
the "recommended" document preparation environment at MIT
|
Owner
|
Completion
|
Estimate of Effort
|
Optimistic
|
Likely
|
Pessimistic
|
amb
|
|
|
|
|
Task:
Certify that the right issues have been resolved, that the
documented Criteria are met, and that the Sponsor is satisfied
with what has been delivered.
|
|