Reporting: Known deficiencies
There are several deficiencies that have their roots in the way data is stored. The only remedy is a change of that design
Budget
- Budget and reports on budget are based on anual totals. Reporting on changes of the budget thus must be based on line item informa-tion. Due to resource constraints, new budget documents will not be implemented in standard in 1998.
Open items / actuals
- The new update functionality (4.0C) will improve the situation. Please refer to the material on 4.0 development news