Voting Results on 1999 Development Requests


In December 1999, the HERUG group was asked to vote on a  list of development requests.  Each HER member was allocated 50 votes to distribute amongst the requests. Voting closed on January 21, 2000. Nineteen HER organizations submitted votes. The table below shows the vote totals, ranked by number of votes.

 

Item

Description

Votes

15 Structural funds centre authorisations
202
3 CO report enhancements
181
11 FM account assignment history / multiple display option
95
6 CC Group movement enhancement
94
14 HR information to be held against the fund and fund centre master
61
13 Sales & Distribution sales order processing - billing plan type
60
24A Maintenance of authorisations 1
54
10 Historical information retention
47
24B Maintenance of authorisations 2
46
12 Sales & Distribution integration with FM in sales order processing
40
25 Integration of HR-FPM (funds and position management) and PS (project system).
29
28 Teaching assignments
21