project name: Internet Transaction Server (ITS)
project leader: Mark Damian
report date: August 29, 2000
submitted by: Mark Damian
url: web.mit.edu/its-alive
Accomplishments past period:
------------------------------
- Production ITS server was up and running on 8/28 as scheduled
- Transactions are being processed in a controlled environment in Production
- Added more features to journal voucher transactions
- Development 50% done on verification of VISA charges functionality
- Worked with Dan Hart, Peter Kelley, and Mark Sprague to modify the ITS Change
Control Process
Goals for the coming period:
----------------------------
- Increase size of Pilot to about 20 users by the end of September
- Evaluate SAP 4.6D ITS patch to fix web reporting bugs
Issues:
---------
- The SAP 4.6C upgrade is starting and its going to take some resources away
from our project.
- The SAP 4.6D ITS patch is still not generally available from SAP. We would
like to wait until its installed prior to rolling out to the community.
Team Dynamics:
-----------------
Sense of relief that we are meeting our latest deadlines and are nearing project
completion.