MIT Telecommunications Facilitities

Functional Requirements For Networking

Tom Coppeto
MIT Information Systems
Last Updated 31 July 1998

Background

The wiring plant serving today's MIT campus network was built in 1988 as part of the 5ESS phone switch installation. Facilities were constructed from existing utility spaces. Some of these utility spaces were specifically designed for telecommunication purposes while others were inserted into electrical, mechanical or janitorial spaces. Yet other telecommunications facilities were left in corridors, offices, labs and shafts.

The goal of the 5ESS project was to provide MIT with a world class telephone system across a campus ranging from state of the art buildings to those constructed before telephones were seen as a good idea. The campus network's use of the 5ESS wiring plant was yet to be realized in 1988. Today the network has outgrown many of the facilities. As we witness increasing numbers of computer networked applications such as SAP, distance learning and the world wide web, the demands on the campus network infrastructure require greater and new technololgies, devices and wiring. The problem statement is simple. Where to put it.

Growth

The campus network infrastructure has grown in many dimensions. The number of devices located in the facilitites to serve the campus network increased sharply from the launch of the modern day network in 1991 and again with bringing the dormitories on line in 1994. However it continues to rise in response to growing numbers of connections and changing technologies.

The initial standards for networking specified 1 network connection per telephone at a time when the number of computers on campus was a small. Today, there are over twice as many active computers than telephones and the advent of more flexible computing with laptops resulted increasing amounts of port capacity in the facilities. The design studios in buildings 5 and 7 and the classrooms in building E51 have further pushed the envelope by providing each student with one or more direct network connections.

The renovation of building N42 realized the need for greater reliability. performance, and centrally managed network connectivity by increasing the number of connections in team and meeting rooms and providing each staff workstation with 3 direct network connections (half the number of electrical sockets per workstation). These projects have set new standards from which the Institute is building upon in new projects such as the classrooms in buildings 2 and 4, the studios in buildings 33 and 10, the renovation of Baker House and the dozens of smaller construction efforts in progress this summer. The demands on the infrastructure will continue to rise.

The campus network is a growing infrastructure. Like the electrical plant, we will see flexible and ubiquitous access to the network. However, the network is growing in yet another dimension.

The network must also respond to growth by meeting increasing demands of load and performance. Larger equipment with multi-gigabit backplanes and low port density are required to meet these demands.

Renewal

Periodic renewal of the network infrastructure is necessary to track growth, maintain alignment with changing technologies and operate equipment with limited life-spans. Equipment serving the campus network is replaced every 4 years on average. Equipment purchased more than 4 years ago is obsolete and because the technologies change so rapidly, we do not know what equipment we will purchase 4 years from now.

Renewal of the wiring plant is an essential part of the long term health of the campus network although not considered in the existing renewal models.

Facilities cannot be designed around specific vintages of equipment or wiring topologies. They must offer enough flexibility to allow for periodic renewal, staging and the introduction of new technologies.

Directions For Networking

In the near term, we will see increasing numbers of connections via unshielded twisted pair wiring, from classrooms wired to the seat to laboratories and large office environments with several connections per station. Some of the closets today already house 500 connections and these numbers continue to climb.

The equipment used in the early days were small and could easily be mounted on a wall alongside the wiring blocks. Today's equipment mounts in 19 inch racks requiring front, rear and side clearance for access to the wiring blocks, wiring coming from the front or the rear of the quipment and ventillation fans. Some of the equipment we see today weighs over 70 pounds and can exceed 3 feet in height, each serving 50-200 connections. The trends in larger equipment continues and the question not only becomes can a 19 inch rack be wedged into an existing facility, but how many.

The wiring itself has changed may change radically in the coming years. Traditionally, we have used a compact type of connector called an rj21 that allows 12 connections to be hubbed together on a single connector. These connectors are much rarer to find today and do not exist in today's hugh performance equipment. Moving to a modular rj45 connections in the facilities creates much more flexibility in adopting new technologies however, the space required for wiring and cable management can increase by a factor of 2.

Finally, what will likely be in the future is a move away from unshielded twisted pair wiring for desktop connections to fiber optic cables. Because of their sensitive nature, the terminations need to be carefully managed and protected, again further increasing the demands on the space.

Facility Specifications

This section is based on the Telecommunications Systems - Design Outline For Academic, Research and Residential Buildings Space Requirements for Telecommunications Facilities Document.

Facility Types

The types of spaces for a complete telecommunications infrastructure are as follows:

Common Facility Requirements

The requirements common to all of the above facilities are as follows.

Facility Location Requirements
  1. Facilitites must be located in dedicated spaces. Other storage, mechanical or janitorial functions should not interfere with the facility.
  2. Facilitites and cable pathways must be located away from sources of electromagnetic interference.
  3. Facilities must be located in dry areas and preferably away from water sources and pipes.
  4. Facilities should have access to main corridors to facilitate needed work and repairs on a 24 hour basis. Facilities should not be located in departmental alarmed areas.
  5. Facilities cannot exceed 250 feet from the furthest point served as measured through the common horizontal cable path.
  6. It is preferable that all facilities within a building be stacked on top of each other to minimize cable runs and help meet distance limitations.
Common Facility Interior Requirements
  1. Facilities must be well lighted.
  2. Facilities must contain a grounding terminal with a #6 AWG wire to approved ground.
  3. Conduits, sleeves and floor penetrations must be fire stopped with ATSM E814 or UL 1479 qualified putty seal.
  4. Facilities should have a minimum of 4 20A 120V duplex outlets, two on emergency power, two not on emergency power. It is preferable that multiple outlets be installed on each wall.
  5. The minimum ceiling height in 90 inches. The minimum door height in 80 inches. The minimum door width in 36 inches.
  6. 3/4" plywood boards should be installed along the walls, a minimum of 72 inches tall.

Requirements Specific to Facility Type

Service Entrance Requirements

Telecommunications lines and cables on the MIT campus of provided via an underground duct system. The duct system to a building is normally composed of 4" conduits. The number of conduits in a duct bank is based on the number of telecommunication lines that could potentially be provided to the building. The estimates of the number of telecommunications lines necessary are based upon the potential number of users in that building. Offices, laboratories, classrooms and residences are assumed to require 1 telecommunications outlet fed from an underground line unless more is requested during the design stage in addition to other needs such as fiber optic cabling to serve the building network.

Number of Underground lines4" conduits required
1-303 conduits
31-604 conduits
61-1805 conduits
181-3006 conduits
301-4807 conduits

All entrance point conduits should be galvanized steel and concrete encased.

Building Distribution Frame (BDF) Requirements

Usually, the BDF is located in the basement. 4" EMT conduits must be installed from the service entrance point to the BDF. The BDF houses outside plant cable termination, cable protection units, power supplies, optical cable light interface units, riser cable interface junctions, cable television equipment, network cabling and equipment mounted in 19" racks and end station wiring.

Number of Connections in BDFSpace Required
1-3060sf
31-60100sf
61-180150sf
181-300200sf
301-480250sf
Intermediary Distribution Frame (IDF) Requirements

These facilitites feed end locations such as connections to offices and classrooms. These closets must be within 250 feet of the furthest point they serve and preferably stacked with floor corings and conduit sleeves connecting them. IDF's house end station termination junctions for voice, data and catv services, termination of riser cables, power supply units and netwlrking equipment mounted in 19" racks. The size of the IDF should be determined by the total potential number of connections the floor can support.

Number of Connections in IDFSpace Required
1-5040sf
51-10060sf
101-20080sf
201-400120sf
401-800160sf
801-1600220sf

Determining Number of Connections

Each space design will influence the number of connections required but to do facility planning the total number of potential connections needs to be esitimated. A networked classroom will require more connections per square foot than an office. The table below is an estimate based on space type.

Space TypeNumber of Connections
classroom1 per seat
computer cluster2 per 40 square feet
design studio2 per seat
meeting room4 per 80 square feet
laboratory2 per 80 square feet
lobby2 per 160 square feet
lounge2 per 80 square feet
office4 per 80 square feet
residence4 per pillow

Facility Classifications

Although MIT has a wide variety of facilitites, they can be classified into 3 categories for the purpose of determining priorites for replacement. Issues such as access, security and resistance to floods, dirt, falling plaster, ladders and power outages have not been included in this classification.

Facilities

The following table lists the existing active telecommunications closets and their corresponding classifications. There are many closets not listed here that do not currently contain active network equipment although they may in the future. Data on these inactive closets is not currently available but should be considered.

main campusclassification
M1-101J III
M1-142 I
M1-167J III
M1-201J III
M1-267J III
M1-301J III
M1-367J III
M2-052T III
M2-154T II
M2-350J III
M3-014T III
M3-082 III
M3-132T III
M3-232T III
M3-332T III
M3-351 III
M3-432T III
M3-454T II
M4-032T I
M4-201J III
M4-215J II
M4-267J III
M4-301J III
M4-369J III
M4-428T II
M5-007J III
M5-105E III
M5-135T III
M5-303E III
M5-428T II
M6-008J III
M6-132T III
M6-208J III
M6-308J III
M6-408J III
M7-208E III
M7-242E III
M7-300T III
M7-336T III
M7-400T II
M8-113J III
M8-213J III
M8-313J III
M8-413J III
M9-038T II
M9-250T II
M9-350T II
M9-450T III
M9-550T III
M10-089T III
M10-140T III
M10-269T III
M10-350T III
M10-400T III
M10-455T I
M11-173T I
M11-221T II
M11-315T II
M11-402T II
M12-065T I
M12-093T III
M13-2002T I
M13-2087A I
M13-2155B I
M13-4002 I
M13-4087A I
M13-4155B I
M14-0658T III
M14-0726T III
M14E-210T III
M14E-301T II
M14N-308 III
M14S-139T III
M16-004T II
M16-104T II
M16-204T II
M16-304T II
M16-404T II
M16-504T II
M16-604T II
M16-704T II
M16-804T II
M17-010 III
M18-034E III
M18-234 II
M18-434E II
M24-018 III
M24-101T II
M24-205E III
M24-307E III
M24-603 III
M26-062A III
M26-100A III
M26-262T III
M26-362J III
M31-0011C III
M31-162J III
M33-022T I
M33-122T I
M33-222T II
M33-322T I
M33-422T I
M34-201T II
M34-401T II
M35-123T II
M35-220E II
M35-320E II
M35-420T II
M36-002M II
M36-192T II
M36-492T II
M36-692T II
M37-075T III
M37-262T II
M37-364T II
M38-193T II
M38-293T II
M38-393T II
M39-340T III
M41-209T III
M41T-118 II
M42-122 III
M44-111 II
M45-192T II
M48-031T III
M48-212T III
M48-338T II
M48-434T III
M50-027T II
M50-210 II
M51-008 II
M54-1133 II
M54-1333 II
M54-1533 II
M54-1733T II
M54-533 II
M54-933 II
M54-333 III
M56-166T II
M56-266T II
M56-366T II
M56-466T II
M56-566T II
M56-666T II
M56-766T II
M57-116T I
M62-103J III
M62-203J III
M62-303J III
M62-403J III
M62-503J III
M62M-007 III
M64-104J III
M64-304J III
M64-504J III
M66-050T II
M66-251T II
M66-351T II
M66-451T II
M66-551T II
M68-005 II
M68-077T II
M68-140T III
M68-218T III
M68-284T II
M68-318T III
M68-384T II
M68-418T III
M68-484T II
M68-518T III
M68-584T II
M68-618T III
M68-684T II
east campusclassification
E2-041T I
E2-144 III
E2-243 III
E2-342 III
E2-443 III
E10-111A III
E10-233T III
E15-003T II
E15-240T II
E18-224T II
E18-302T II
E18-402A II
E18-577T II
E18-677T II
E19-019T II
E19-216T I
E19-316T I
E19-416T I
E19-516T I
E19-616T I
E19-716T I
E23-340T III
E25-111T II
E25-157T III
E25-301T II
E25-353T II
E25-507T II
E25-554T II
E28-102T II
E32-001 III
E34-200T III
E34-476T III
E38-301E II
E38-601E II
E39-202T III
E40-006T II
E40-105T II
E40-205T II
E40-305T II
E40-405T II
E48-200T II
E48-248T II
E51-017T II
E51-043T III
E51-117T II
E51-181T II
E51-217T II
E51-255T II
E51-283T III
E51-317T II
E51-357T II
E52-035T II
E52-105T II
E52-161T III
E52-245T II
E52-262T II
E52-329T II
E52-371T II
E52-414T II
E52-471T II
E52-520T II
E52-558T II
E53-014T I
E53-291T III
E53-332T II
E55-006T II
E55-100T II
E55-1010T II
E55-1313T II
E55-1616T II
E55-1919T II
E55-2222T II
E55-2525T II
E55-2828T II
E55-404T II
E55-707T II
E56-002T II
E56-302T II
E60-050T II
north campusclassification
N10-118 III
N42-043T I
N42-145T I
N42-245T I
N51-118T III
N51-218T II
N52-123T II
N52-323T II
N52-423T II
N57-235 II
NE20-208 II
NE20-241 II
NE20-309 II
NE20-4008T II
NE25-270B II
NE25-4118T II
NW10-006T II
NW10-026T II
NW10-129T II
NW10-304T II
NW10-325T II
NW12-134A III
NW12-313 III
NW14-0105 III
NW14-0310T II
NW14-2105 III
NW14-2310T II
NW14-4105 III
NW17-028T II
NW17-126T I
NW17-226T II
NW61-134 III
NW61-210 III
NW61-240 III
NW61-410T III
NW61-440T III
NW62-246 II
west campusclassification
W1-009T II
W1-013T I
W1-028T II
W1-101T II
W1-120T II
W1-200T II
W1-220T II
W1-300T II
W1-320T II
W1-400T II
W1-420T II
W1-500T II
W1-520T II
W1-600T II
W1-620T II
W2-001 II
W4-012T II
W4-135T II
W4-242T III
W4-302T II
W4-342T III
W4-602T II
W4-642T III
W5-001T II
W7-010T II
W7-107T II
W7-130T II
W7-207T II
W7-230T II
W7-307T II
W7-330T II
W7-407T II
W7-430T II
W7-507T II
W7-530T II
W7-607T II
W7-630T II
W8-003T II
W11-080T II
W13-002A III
W13-007 III
W13-008T III
W13-010C III
W16-018A II
W20-014T I
W20-100T II
W20-410T II
W20-574T III
W31-0057 II
W31-212 II
W31-305B II
W32-139 II
W34-125T II
W34-146MT II
W51-010A II
W51-030A II
W51-210T III
W51-240J III
W51-410T III
W51-440J III
W53A-102T II
W59-000T II
W59-135T I
W61-0056T II
W61A-201E II
W61A-301E II
W61B-101E II
W61B-301E II
W61C-201E II
W61D-101E II
W61D-301E II
W61E-201 II
W61F-201 III
W61F-401 III
W61G-201E III
W61G-401 III
W61H-202E III
W61H-402E III
W61J-101E III
W61J-102B III
W61J-201E III
W61J-402E III
W70B-117T III
W70D-122T III
W70F-127T III
W71-168T III
W71-275T III
W71-317T III
W84-1205T III
W84-1505T III
W84-1805T III
W84-2105T III
W84-2405T III
W84-305T III
W84-605T III
W84-905T III
W85-1003J III
W85-1203J III
W85-1403J III
W85-1603J III
W85-203J III
W85-403J III
W85-603J III
W85-803J III
W85B-100LA III
W85E-100LA III
W85G-100LA III
W85J-100LA III
W89-109 II
W89-125T II
W91-140T I
W92-164T I
W92-264T I
WW15-070Z II
WW15-148T II
totalsclassification
34 closetsI
209 closetsII
160 closetsIII