NOTE:
For best printed quality, get the paper Quick
Reference Card from the Paper
Documents
web page. MIT
personnel can order free copies from Copy Technology
Centers or download the PDF files directly. Go
to Initial Screen From
the SAP User Menu screen: Navigation
Path: - User Menu Transaction
Code : /nzstm Result: Three tabbed
screens are displayed for you to enter all the selection criteria
for running the Summary Statement. Complete the Selection
Criteria screen first before moving to the next one. Move
between the screens by clicking on the tab. Step
1: Complete the Selection Criteria Entry Screen
Check
this box to see all lower WBS's under the WBS element
that you entered. 8)
9)
Step
2: Complete the Print Options Entry Screen Use this screen
if you are printing immediately.
Step
3: Complete the Column Options Entry Screen Type over the default
numbers to the right of the columns in the order that
you want the columns to appear on the report. Leave
a field blank to exclude that column from the report. Click the Execute button
to run the report. Review
Transaction Totals: (Level 1) The
main report screen shows totals for all transactions posted
against the cost element group, cost object, project, or profit
center that you selected on the entry screen. Expand
All: Displays
the most detailed view of the cost element group, showing
a breakdown of transactions by cost elements. Expand:
Shows
incrementally the more detailed levels of the cost element
hierarchy. Download:
Allows
you to download the report to a spreadsheet.
Cost
Object: Click
on the highlighted cost object to display Master Data
about it. Costing
Sheet:
Used
to calculate F&A (formerly overhead) and employee
benefits.
List
of cost elements for the cost object activity. Usually
for internal orders and WBS elements (this section
is not displayed for the CEMIT-0 cost element
group) Default
budget values (or departmental plan): Click
on an amount to drill down to the budget
listing. Current
month's actual expense. All
activity on a cost object by cost element for the fiscal
year-to-date. The Fiscal YTD column shows amounts up
to the current fiscal period vs. the Commitment column
which shows amounts as of the run date of the report.
Click
on an amount in the Fiscal YTD column (4) to
drill down to the Detail Transaction Report.
Scroll
right to see more columns, if necessary. Sum
of cumulative expenses to date by cost element. For
cost centers, this sum matches the fiscal year activity.
For internal orders and WBS elements, it is from the
inception of the cost object. Drill
Down to Budget Listing (Level 2) Click on an
amount under the Budget column (2) to see the budget
listing for the fiscal year (shown below). Cost
El: Cost
element number Period: Fiscal
month and fiscal year Click the Cancel button Drill
Down to Detail Transaction Report (Level 2) This
level shows the detailed list of transactions (DTR) used to
calculate the totals on the main screen of the Summary Statement.
Drill
Down to Source Document (Level 3) The
source document shows information on the original SAP document
for each transaction such as a requisition or a journal voucher.
Summary
Statement
QUICK
GUIDE
Step
1: Complete the Selection Criteria Entry Screen
Step
2: Complete the Print Options Entry Screen
Step
3: Complete the Column Option Entry Screen
Review
Transaction Totals (Level 1)
Drill
Down to Budget Listing (Level 2)
Drill
Down to Detail Transaction Report (Level 2)
Drill
Down to Source Document (Level 3)
- Role ZMIT
- Reports
- Summary Statement
Optional
fields
To
limit the WBS levels for the WBS element you entered,
type in the level no. (2-5).
Type
in the cost object if you don't know the cost object type
and press the Enter/Return key. The numbers appear in
the correct cost object field above.
Click
to include cost objects by term code; deselect to omit
them:
open
for charges between start and end dates of cost
object
active
but in the closing period
no
longer in use
completely
closed; charges not allowed
Enter
the MIT ID of the cost object's supervisor. All cost objects
for the supervisor for which you have authorization
will be displayed on the report.
Check to exclude
blanket orders from the Commitment column.
Type
in a title for a consolidated report.
Check this
field only if you want your report executed and
printed immediately but not displayed on the screen. Type
in the printer name you want the report sent to.
Summary only
or
Prints only the Summary Statement.
Summary
and DTR
Prints
the Summary Statement and the Detail Transaction
Report at the same time.
Summary
Printing Options
Landscape
or
Prints
the report horizontally (11 x 8 1/2).
Portrait
Prints
the report vertically (8 1/2
x 11).
If
you select five or more columns on the Column
Options screen (next tab), the Summary Statement
columns will be printed on two pages. The
first page will contain the Description
column first, which is the column listing
the cost elements, and then the four columns
you selected. The rest of the columns will
be on the second page with the Description
column again as the first column.
Simplex
or
Prints the
report single-sided.
Duplex or
Prints
the report double-sided (only on duplex printers).
Printer Default
Prints
the report single
or double-sided according to the printer's default.
DTR
Printing Options
Same
as for the Summary Statement (2c).
Click the
Column Options tab.


Report
Buttons
Shows
incrementally the less detailed view of the cost element
hierarchy.
Shows
the most compressed view of the report with the least
amount of detail.
Displays
the Detail Transaction Report.
Principal:
For
endowment internal orders
Expenses:
For
all cost objects
Revenue:
For
internal orders, WBS elements, and some cost centers
Settlement:
Cost
centers:
Office
of Budget and Financial Planning for the current
year
Internal
orders:
No
budget, except for Dept. of Facilities
WBS
elements:
Authorized
total specified by the sponsor; appears in cost
element 400000
Click
on an amount in the Current column (3) to drill
down to the Detail Transaction Report, a list of individual
transactions that make up the transaction total.

Click
on an amount in the Cumulative column (5) to drill
down to the Detail Transaction Report.
Difference
between the Budget and Cumulative columns.
All
open commitments (as of the run date of the report) against
the cost object. Current commitments are shown regardless
of the month and year selected.
Click
on the Commitment column (7) to view a list of
commitments on the Detail Transaction Report.
Difference
between the Unexpended and Commitment columns.


Budget
Listing
Amount
budgeted for the fiscal period
(not
shown)Shows
the cost object number reported on
to return to the Transaction Total (Level 1).

to return to the DTR (Level 2).
SAP for MIT Documentation on the Web
Valid From: 12/06/2001