TSM 5.4





Project Start:
Project Finish:
Wed 1/17/07
Thu 5/17/07


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Project Started
0 daysWed 1/17/07Wed 1/17/07 100%
2      
3
Determine need for TSM 5.4 SWRT project
5 daysThu 1/11/07Thu 1/18/07Deb,Al,Atticus,Patrick,Dave99%
4
Go - No Go
1 dayThu 1/11/07Thu 1/11/07 100%
5
Determine PRC(s)
4 daysFri 1/12/07Thu 1/18/07 100%
6      
7
Form Release Team
4 daysThu 1/11/07Wed 1/17/07Dave[125%],Deb[125%],Atticus[125%],Al[125%],Patrick100%
8      
9
Project Plan
62 daysWed 1/17/07Fri 4/13/07 100%
10
Create Project Plan
12 daysWed 1/17/07Thu 2/1/07Dave100%
11
Update project Plan
50 daysFri 2/2/07Fri 4/13/07Dave100%
12      
13
Kickoff meeting
1 dayThu 1/18/07Thu 1/18/07Team100%
14
Meeting time and minutes
1 dayThu 1/18/07Thu 1/18/07 100%
15
Review team member roles
1 dayThu 1/18/07Thu 1/18/07 100%
16
Discuss project criteria - I.e. nogo
1 dayThu 1/18/07Thu 1/18/07 100%
17
Review and refine Project Plan
1 dayThu 1/18/07Thu 1/18/07 100%
18
Review Project underway announcement
1 dayThu 1/18/07Thu 1/18/07 100%
19
Discuss deliverables
1 dayThu 1/18/07Thu 1/18/07 100%
20
Discuss next steps
1 dayThu 1/18/07Thu 1/18/07 100%
21      
22
Ongoing Project Tasks
52 daysWed 1/17/07Fri 3/30/07 92%
23
Weekly TSM SWRT Release Team meetings
52 daysWed 1/17/07Fri 3/30/07Team90%
24
Weekly update of project to Help Desk staff
52 daysWed 1/17/07Fri 3/30/07Karl90%
25
Update installers based on testing results
30 daysMon 2/5/07Wed 3/21/07Atticus100%
26      
27
Documentation - Review and update pages as neccesary
53 daysMon 2/5/07Fri 4/20/07Esther,Team75%
28
Product front door
19 daysMon 2/5/07Fri 3/2/07 75%
29
Version, requirements
9 daysMon 2/5/07Thu 2/15/07 75%
30
Installation
9 daysMon 2/5/07Thu 2/15/07 75%
31
Upgrade
9 daysMon 2/5/07Thu 2/15/07 75%
32
Known issues
9 daysMon 2/5/07Thu 2/15/07 75%
33
New features
9 daysMon 2/5/07Thu 2/15/07 75%
34
Installer readme(s)
10 daysFri 2/16/07Fri 3/2/07 75%
35
Desupport announcement
10 daysFri 2/9/07Fri 2/23/07 75%
36
Related links
10 daysFri 2/23/07Thu 3/8/07 75%
37
How to configure
10 daysFri 2/23/07Thu 3/8/07 75%
38
First login
10 daysFri 2/23/07Thu 3/8/07 75%
39
Setting up the scheduler
10 daysFri 2/23/07Thu 3/8/07 75%
40
New topics
10 daysWed 3/7/07Tue 3/20/07 75%
41
Review and update preceding documentation
20 daysFri 3/23/07Fri 4/20/07 75%
42      
43
Documentation completed
0 daysFri 4/20/07Fri 4/20/07 75%
44      
45
Communication planning
69 days?Wed 1/17/07Wed 4/25/07 78%
46
'Release Underway' announcement
40 daysFri 1/19/07Fri 3/16/07 100%
47
Draft 'Release underway' announcement
9 daysFri 1/19/07Wed 1/31/07Patrick100%
48
Team review of 'Release underway' announcement
6 daysThu 2/1/07Thu 2/8/07Release Team100%
49
IST-COMM review of 'Release underway' announcement
3 daysFri 2/9/07Tue 2/13/07Patrick100%
50
Send 'Release underway' announcement
0 daysTue 2/13/07Tue 2/13/07Patrick100%
51
Vista/TSM announcement/documentation coordination
1 dayThu 1/25/07Thu 1/25/07Deb100%
52
Prepare Late announcement (if needed)
6 daysFri 3/9/07Fri 3/16/07 100%
53
Draft 'delayed' announcement
2 daysFri 3/9/07Mon 3/12/07 100%
54
Team review of 'delayed' announcement
2 daysTue 3/13/07Wed 3/14/07 100%
55
IST-COMM review of 'delayed' announcement
1 dayThu 3/15/07Thu 3/15/07 100%
56
Send 'delayed' announcement
1 dayFri 3/16/07Fri 3/16/07 100%
57      
58
MIT Community informed of Project underway
0 daysTue 2/13/07Tue 2/13/07 100%
59      
60
Communication articles
1 day?Wed 1/17/07Wed 1/17/07 100%
61
Digitalk
1 day?Wed 1/17/07Wed 1/17/07Esther100%
62
IS&T newsletter
1 day?Wed 1/17/07Wed 1/17/07Esther100%
63
Bits and Bytes article
1 day?Wed 1/17/07Wed 1/17/07Esther100%
64
Spotlight mac and Windows - June/July
1 day?Wed 1/17/07Wed 1/17/07Esther100%
65      
66
'Product available' announcement
8 daysFri 4/13/07Wed 4/25/07 0%
67
Draft 'Product available' announcement
3 daysFri 4/13/07Wed 4/18/07Patrick,Dave0%
68
Team review of 'Product available' announcement
1 dayThu 4/19/07Thu 4/19/07Team0%
69
IST-COMM review of 'Product available' announcement
4 daysFri 4/20/07Wed 4/25/07 0%
70      
71
Create installers
44.5 daysThu 1/18/07Thu 3/22/07 100%
72
Acquire pre-release candidate vendor code
10 daysThu 1/18/07Wed 1/31/07Atticus100%
73
Create TSM 5.4 Mac installer
20 daysThu 2/8/07Mon 3/12/07Atticus100%
74
Create TSM 5.4 Windows installer
14 daysFri 2/2/07Mon 2/26/07Atticus100%
75
Update documentation for installers based on test feedback
20 daysFri 2/9/07Thu 3/22/07Esther100%
76
Update TSM installers with production code
2 daysThu 2/1/07Fri 2/2/07Atticus100%
77      
78
Test phase
50 days?Fri 2/2/07Fri 4/13/07 100%
79
Create test matrix
5 daysFri 2/2/07Thu 2/8/07Deb100%
80
TSM release team testing
25 daysMon 2/26/07Fri 3/30/07Team100%
81
Review internal testing results
1 dayMon 4/2/07Mon 4/2/07Team100%
82
Help Desk Testing started
9 daysTue 4/3/07Fri 4/13/07Karl100%
83
Make available to outside testers
9 daysMon 4/2/07Thu 4/12/07Team100%
84
Review testing results
1 day?Thu 4/12/07Thu 4/12/07Team100%
85
build a list of stock Q&A's
35 daysFri 2/23/07Thu 4/12/07Esther,Team100%
86      
87
Product testing completed
0 daysThu 4/12/07Thu 4/12/07 100%
88      
89
Training
25 days?Thu 2/8/07Thu 3/15/07 100%
90
Quick Start
25 days?Thu 2/8/07Thu 3/15/07 100%
91
Determine people resource availability
5 daysThu 2/8/07Wed 2/14/07 100%
92
prepare for QS
15 daysThu 2/22/07Wed 3/14/07Esther100%
93
Quick Start
1 day?Thu 3/15/07Thu 3/15/07 100%
94      
95
Help Desk training
9 days?Thu 2/8/07Wed 2/21/07 100%
96
Determine people resources
5 daysThu 2/8/07Wed 2/14/07 100%
97
Prepare for training - Documentation
1 day?Thu 2/15/07Thu 2/15/07 100%
98
Do training
1 day?Fri 2/16/07Fri 2/16/07 100%
99      
100
Prepare for Quick Start
2 days?Tue 2/20/07Wed 2/21/07 100%
101
Determine people resources
1 day?Tue 2/20/07Tue 2/20/07 100%
102
Prepare for Quick Start - Documentation
1 day?Tue 2/20/07Tue 2/20/07 100%
103
Do Quick Start
1 day?Wed 2/21/07Wed 2/21/07 100%
104      
105
Training completed
0 daysThu 3/15/07Thu 3/15/07 100%
106      
107
Delivery
8 daysTue 4/17/07Thu 4/26/07 0%
108
Team agreement to deliver product(s)
3 daysTue 4/17/07Thu 4/19/07 0%
109
Move documentation to production
3 daysMon 4/23/07Wed 4/25/07 0%
110
Make installer publicly available
1 dayThu 4/26/07Thu 4/26/07 0%
111
Send product available announcement
0 daysThu 4/26/07Thu 4/26/07 0%
112      
113
Product announced and delivered
0 daysThu 4/26/07Thu 4/26/07 0%
114      
115
30 day followup meeting
1 dayThu 5/17/07Thu 5/17/07 0%
116
Discuss issues that may have occurred since product release
1 dayThu 5/17/07Thu 5/17/07 0%
117
Plus/delta
1 dayThu 5/17/07Thu 5/17/07 0%
118      
119
Project completed
0 daysThu 5/17/07Thu 5/17/07 0%






Microsoft Home Page
Microsoft Project Home Page