Use these steps to reject all line items for a billing request - for example, to enable quarterly billing.
Note: This transaction is the only way to modify a billing request after the billing block has been removed. For billing requests that are blocked, you should use V.23.
Role ZSBM=>Cost Reimbursable=>Sales Orders=> VA02 - Change Sales Order
At the Command Line, enter: /nVA02
Order (Enter bill request number; range is 70000000 - 79999999)
The Change Project Bill Request: Overview screen displays, as shown below.
To reject all line items on the billing request (for example, to enable quarterly billing),
Result: All line items are selected (the line item background turns yellow and brown), as shown below.
The Change Reason for Rejection window opens, as shown in the next step.
Result: The reason for rejection displays on the overview screen, as shown below. The Net value (at upper right, as shown below) should now equal 00.0.