ZVA1 - Change Sales Order via WBS Element


Use these steps to display or change a sales order for a WBS element.

  1. Get started (SAP menu path, fast path)
  2. Change sales order via WBS element: initial screen
  3. Change project order: overview
  4. Change project order: header data
  5. Change project order: item data
  6. Save changes

1. Get Started


2. Change Sales Order via WBS Element: initial screen

  1. Enter order number: (7-digit WBS element)

    Change Sales Order via WBS Element: initial screen

  2. or F8 to Execute.
    The Change Project Order: Overview screen displays.

3. Change Project Order: overview

See step 3 of "VA02 - Change Project Order".


4. Change Project Order: header data

See step 4 of "VA02 - Change Project Order".

 


5. Change Project Order: item data

See step 5 of "VA02 - Change Project Order".


6. Save changes

 