Project Planning Matrix |
SUMMARY of OBJECTIVES or ACTIVITIES |
OBJECTIVELY VERIFIABLE INDICATORS |
MEANS or SOURCES of VERIFICATION |
IMPORTANT ASSUMPTIONS |
DEVELOPMENT HYPOTHESIS
If the project purpose is achieved, then a contribution is made towards the goal
If these results are obtained, then the project purpose is achieved
|
OVERALL GOAL
to which the project contributes |
INDICATORS
that goal is reached |
|
For sustainability of Overall Goal |
PROJECT PURPOSE |
INDICATORS
which show the achievement of a successful PP |
|
For achievement of the Overall Goal |
MANAGEABLE FACTORS
If these activities are carried out, then these results or outputs are obtained |
RESULTS OR OUTPUTS |
INDICATORS,
describing the Results or Outputs |
|
For achievement of the Project Purpose |
ACTIVITIES |
SPECIFICATIONS
of Quantities and Unit or Costs for each individual activity |
|
For obtaining the Results |