Find out what's under construction on or near campus
Subscribe to receive notifications of construction updates.
December 30, 2024
Building 6C
Beginning Monday, December 23, a portion of the first-floor corridor of Building 6C is scheduled to close as crews perform flooring repair and refinishing work. The affected corridor contains the Bars of Color within Squares terrazzo art piece on the first floor of Building 6C. Work hours are 6AM-3PM. Some intermittent noise from buffing machines and a vacuum is anticipated. This closure is scheduled through Wednesday, January 8.
During this time, there will be no access through this corridor except as emergency egress. Occupants are encouraged to use the southern corridor in Building 6C to access the elevator, stairwell, and adjacent spaces. Signage will be posted directing occupants to alternate pathways.
Questions may be directed to Marc Truant.
[to top]
Building 11
On Monday, December 23, construction of the new Undergraduate Advising Hub on the first floor of Building 11 is scheduled to begin. Anticipated work hours are weekdays from 6AM-2PM. Heavy noise is planned to conclude by 8AM daily, with some occasional light noise for the duration of the workday. Signage will be posted. This project is scheduled through July.
Questions may be directed to Laura Mancuso.
[to top]
Building 32
As part of the Institute’s investment in infrastructure renewal, crews are scheduled to renovate the façade of Building 32. This work includes masonry and metal panel renewal, and cleaning and restoring the surfaces of the façade and some roof sections. Construction hours are 7AM – 3PM. During construction, some local noise and vibration are expected. This project is scheduled to continue through January 2026.
Construction is planned to be completed in phases, beginning at the Compton Court Stairs, the Elevator Tower, and the Peter Tower. The project team is working closely with the occupants impacted by this work and has been meeting with key contacts in each area to review the proposed schedule and share the scope of work associated with the project.
Phase 2a: July 2024 through February 2025
Construction activities are underway with the installation of scaffolding and swing staging for Phase 2a at the Compton Court Stairs, the Elevator Tower, and the Peter Tower. The Compton Court Stairs will be inaccessible during this phase. The scope of work includes masonry repairs, stair tread repointing, selective metal façade and roof panel replacement and installation, sealant replacement, and the cleaning of the façade and panels.
Phase 2b: February 2025 through January 2026
Beginning in February of 2025, the areas of work will switch for Phase 2b, which will include the Dreyfoos South Tower, Gates South Tower, Lower Gates East, East Entry, Collier Entry, Lecture Hall 123, and the Amphitheater. During this time, access to the Collier Entry and Amphitheater will be restricted and occupants will be redirected to alternate points of entry throughout the Stata Center.
For this phase, the scope of work will include scaffolding and swing staging installation, masonry repairs, roof installation, roof coping, removal and replacement of deteriorated brick, sealant replacement, and the cleaning of the façade and panels.
See an overview of the project from the info session or the current schedule.
Questions may be directed to Alexander Campbell.
[to top]
Building 56
On Monday, November 18, crews are scheduled to begin construction in the IS&T computer repair room, 56-129, located on the first floor of building of Building 56. This project is scheduled through the end of January. Anticipated work hours are weekdays from 6AM-3PM. Heavy noise is planned to conclude by 9AM daily, with some occasional light noise for the duration of the workday. These activities will be contained within the room. Signage will be posted.
Questions may be directed to Cherie Alexander.
[to top]
Buildings 62 & 64
Construction activities are underway as MIT proceeds with the renovation of East Campus, Buildings 62 & 64, with activities continuing through Summer 2025. Construction hours are 7 AM – 5 PM, Monday through Friday, with some weekend and evening work expected.
Project phases
- Project mobilization in June will include extending fencing along the site perimeter of McDermott Court.
- Beginning the week of July 5, the building site as well as the sidewalk and parking spaces along Ames Street next to Building 64 will be fenced off.
- Demolition activities are scheduled to begin during this time, and traffic will increase in the area.
- Pedestrians will be directed to bypass the construction area and use the eastern sidewalk of Ames Street.
- August 2023 – August 2025: The perimeter fence will extend north of the site near Building 66, where it will remain until the end of the project. Construction work will begin in full.
Gray Way
On Thursday, December 26, deliveries to the Building 62 & 64 work site have been scheduled. During this time, Gray Way (the access road between Buildings 50, 62 & 64) is scheduled to temporarily close to vehicular traffic; pedestrian and cyclist access will be maintained. Delivery access to the area will be maintained through the access road between Buildings 62/64 and 66 from Ames Street.
Also note Gray Way may close occasionally to accommodate additional deliveries to the site throughout the remainder of construction. Signage will be posted.
Questions may be directed to Kevin M Carr.
[to top]
Building 66
Construction is underway on an office suite located in the basement of Building 66. Typical work hours are weekdays from 6AM-2PM. Heavy noise is planned to conclude by 8AM daily, with some occasional light noise for the duration of the workday. These activities will be contained within the room. Signage will be posted. This project is scheduled through early February.
Questions may be directed to Santiago Hernandez.
[to top]
Building E15
On Tuesday, November 12, work is scheduled to begin on the renewal and modernization the passenger elevators in Building E15. The work will include installing new equipment and new cab finishes. Anticipated work hours are 7AM to 3PM, Monday-Friday, with some noisy work scheduled for earlier morning hours. Most of the work will take place in the elevator machine room and elevator shaft. Some minor noise is expected throughout the workday.
The elevators will be renewed one at a time, allowing one to remain operational while the other is out of service. Car #1 is scheduled to be out of service through mid-March. Once completed, Car #2 will be removed from service through the end of July 2025. Signage will be posted.
About this project
This renewal project is part of a broader effort to renew and modernize the elevators and lifts in several different buildings across campus. Modernizing the elevators will replace obsolete equipment, protecting the safety of the MIT community while improving the day-to-day experience of building occupants and visitors.
Questions about this work may be directed to Thanh Nguyen.
[to top]
Building E40
On Monday, December 23, renovation of room E40-351 on the third floor of Building E40 is scheduled to begin. Anticipated work hours are weekdays from 6AM-2PM. Heavy noise is planned to conclude by 8AM daily, with some occasional light noise for the duration of the workday. Signage will be posted. This project is scheduled through the end of January.
Questions may be directed to Maria Theodorou.
[to top]
East Campus: Kendall Square Initiative
For the most up-to-date information about the Kendall Square Initiative, visit the courbanize project profile. Click the “Follow” button to sign up for an account and receive notifications about the project. Learn more about the Kendall Square Initiative.
Construction in Kendall Square kicked off in September 2016. Construction hours are scheduled for 7AM – 6PM weekdays, and Saturday from 9AM – 6PM.
Questions about the construction phase of this work may be directed to Holly Sutherland.
Visit the courbanize project profile to review details about the planned activities and to subscribe to construction updates. Subscribe to notifications by clicking the “Login” button at the foot of the “Comment here” box to sign up for an account, and then “follow” the project.
Patient parking for MIT Health will remain available.
- MIT Health will validate parking for patients. (Cars exiting the lot without validation will incur a non-refundable $60 fine.)
- Cars that are in the lot for more than two hours are subject to towing. If patients have appointments that exceed two hours, MIT Health will contact the Parking Office on their behalf.
General Construction Updates
- Police details will be utilized throughout the project area to assist with pedestrian and vehicular traffic.
- Large equipment will be removed and brought to site on and on-going basis. This activity may occur after hours but no disruptions are expected.
- General construction activities will continue on Saturdays. Work will occur within the City of Cambridge allowable work hours, 9:00 am to 6:00 pm.
See the map for more details.
For information on the Wadsworth Street closure, click here.
Questions about the construction phase of this work may be directed to Holly Sutherland.
[to top]
Building NW13
On January 4 and January 11, Albany Street adjacent to Building NW13 is scheduled to be narrowed to accommodate crane operations as materials are transported to the roof, weather permitting. Anticipated hours are 7AM-3PM. Some noise from the crane and loading activities is anticipated.
Traffic will remain two-way through the area, though vehicles will be intermittently stopped as the street is narrowed to one lane. Several street parking spaces will be restricted in the area. Signage will be posted, and officers will be onsite throughout the duration of the work to direct vehicles, pedestrians, and cyclists. Please be aware and use caution when traversing this area.
Questions may be directed to CJ Smith.
[to top]
Building W41
Construction activities are underway as MIT proceeds with the redevelopment of the Metropolitan (Met) Warehouse, Building W41. The adaptive reuse of the Met Warehouse will provide a new home for the School of Architecture and Planning (SA+P), including classrooms, design studios, research spaces, faculty offices, and areas for meetings and collaborative activities. Additionally, the space will house the new MIT Morningside Academy for Design and create a location for the largest community-wide makerspace on campus managed by Project Manus. The anticipated target completion date for this project is summer 2025.
Below you’ll find an overview and high-level schedule for the major phases of construction. Standard hours are 7 AM – 6 PM, Monday-Friday, with some weekend and evening work expected. Please note that the schedule is subject to change.
Vassar Street sidewalk closure
For the duration of the project, the sidewalk and cycle track adjacent to the building along Vassar Street will close to pedestrians and cyclists for the duration of the project. The westbound cycle track will be detoured to create a shared lane on Vassar Street (the eastbound lane will be unaffected). Pedestrians will be directed to the south side of Vassar Street via existing crossings at the New Vassar Residence Hall and at Mass Ave.
Learn about the Metropolitan Warehouse
To learn more, visit the Capital Projects site.
Contact
Questions about this project may be directed to metwh-reno-info@mit.edu.
[to top]
Albany Street Garage
Beginning on Monday, July 29, the Albany Street Garage (N4) is scheduled to partially close, from levels 2 through the rooftop, in order for crews to implement renewal work including the repair and waterproofing of the structure. Construction hours are weekdays from 7AM-3PM. This renewal work is scheduled through January.
If parking is required during this time period, an N4 parking permit will allow access to the ground level of the garage, along with the N10 parking lot or the 139 Mass Ave Lot (rear). Signage will be posted.
Questions may be directed to Alexander Campbell.
[to top]
Amherst Alley
Utilities work is underway begin in manholes in West Campus. The work sites include areas along Amherst Alley in front of Building W71, the pathway between Tang Hall and Westgate (Buildings W84 & W85), across Audrey Street, and in the Police Station parking lot. Work is scheduled from 7AM through 3PM each day, with noisy work beginning after 9AM near residences. This project is scheduled through December.
A cable pulling truck will be onsite and some low noise from a small generator and pump are expected. The work areas will be cordoned off. Streets and pathways will be accessible throughout this work, though several parking spaces will be restricted in each work area. Signage will be posted.
Questions about this work may be directed to Rich Lucas.
[to top]
Vassar Street
Beginning Tuesday, October 15, overnight utilities work is scheduled to commence along Vassar Street and the southern sidewalk adjacent to Building 35. During this work, the Vassar Street eastbound travel lane, between Massachusetts Avenue and Main Street, is scheduled to close nightly to accommodate the utilities crew; the sidewalk adjacent to Building 35 will be closed throughout the project. Anticipated hours are weeknights from 7PM-5AM. This steam line repair work will generate some noise from concrete cutting. This project is scheduled through January 2025, though it may extend as needed once conditions are identified.
Police will be present during these activities, and the Vassar Street closure area will be clearly marked. Signage will be placed to help direct vehicles, pedestrians, and cyclists. Access to all buildings will be maintained. Please use caution when traveling in the area.
Overnight eastbound lane closure on Vassar Street weeknights
Each weeknight through the subsequent morning, between 7PM and 5AM, crews will establish a protected work zone in the roadway and sidewalk of Vassar Street adjacent to Building 35 with temporary fencing. This work site will impede vehicular travel in the eastbound direction. During these times, Vassar Street from Main Street to Mass Ave will be one-way westbound for vehicles. A temporary cycle lane will be established with protective barriers in the eastbound direction around the site during work hours. For the duration of the project, pedestrians will be redirected to cross the street at Mass Ave and mid-block to the northern sidewalk to bypass the work area.
The travel lane and cycle lane will be plated and reopened each morning, and the temporary fencing moved into the sidewalk area. The cycle lane work area will be plated with recessed, anti-skid plates.
Vehicular detour - weeknights from 7PM-5AM
Eastbound vehicular traffic, including shuttles and buses, will be detoured around the area from Mass Ave to Albany Street onto Main Street each night after 7PM. Access for abutters in Stata Garage, the childcare lot, and the Buildings 37 and 39 underpasses will be maintained from Vassar Street via Main Street.
Shuttle and bus detour - weeknights after 7PM
Beginning at 7PM each weeknight, the Tech Shuttle will be detoured around the area to Albany Street. During these times, the Tech Shuttle stop located in front of Building 35 on Vassar Street (Vassar Street at Mass Ave) will be temporarily relocated to Albany Street in front of Building N10. The MBTA CT2 bus will also be affected; see the MBTA site for details. Please be prepared for potential delays.
See the map for more information.
Questions about this work may be directed to Seth Kinderman.
[to top]
Non-MIT work
DCR TRAFFIC ADVISORY:
Safety Improvements for the BU Bridge Corridor of Memorial Drive in Cambridge
Beginning on Monday, October 7, 2024, and continuing through Friday, October 11, 2024, from 8 p.m. to 5 a.m. and from Tuesday, October 15, 2024, through Tuesday, November 26, 2024, from 7 a.m. to 4 p.m. (with potential night and weekend work) the Department of Conservation and Recreation (DCR) will intermittently close lanes and implement detours along Memorial Drive from Magazine Street to Audrey Street via the BU Bridge rotary in the City of Cambridge to accommodate more than $1.5 million in safety upgrades for pedestrians and cyclists. The safety improvement work includes widening the shared use path leading to the BU rotary; improving and reconfiguring wheelchair ramps and median islands at the intersection of Memorial Drive and the BU Bridge; replacing nearly 700 linear feet of existing Boston Pattern Fence; restriping the crosswalks; and implementing a speed limit reduction to 25 mph along the BU Bridge corridor. Drivers should expect traffic congestion during rush hours and seek alternate routes, if possible. Cyclists are advised to ride at slow speeds with increased caution, stay within marked bike lanes, follow detour signage and lane delineation and yield to pedestrians. Traffic patterns will be clearly marked, and a police detail will be on site.
For more information on the work including a detours and design plans visit DCR’s webpage for the project.
WHERE:
- Memorial Drive from Magazine Street to Audrey Street via the BU Bridge rotary in the City of Cambridge
WHEN:
- 7 a.m. - 4 p.m. (with potential night and weekend work)
For questions about this work, please contact Ilyse Wolberg.
[to top]